Yahoo Answers is shutting down on May 4th, 2021 (Eastern Time) and the Yahoo Answers website is now in read-only mode. There will be no changes to other Yahoo properties or services, or your Yahoo account. You can find more information about the Yahoo Answers shutdown and how to download your data on this help page.
Trending News
Promoted
deircr3
Lv 4
How do I find the slack time of A? http://pic20.picturetrail.com/VOL1370/5671323/24520837/410059420.jpg?
1 Answer
Relevance
- SqdancefanLv 77 years agoFavorite Answer
Draw the critical activities nose-to-tail. See when A must be completed so it doesn't delay the project, then subtract from that the length of A.
The critical path is B-D-E-G. The starting day of each of these is 1, 7, 17, 21, respectively. In order to have A complete by day 17, it must start no later than day 14. Thus, there are 13 days of slack time associated with task A.
Still have questions? Get your answers by asking now.