Yahoo Answers is shutting down on May 4th, 2021 (Eastern Time) and beginning April 20th, 2021 (Eastern Time) the Yahoo Answers website will be in read-only mode. There will be no changes to other Yahoo properties or services, or your Yahoo account. You can find more information about the Yahoo Answers shutdown and how to download your data on this help page.
Trending News
Contractor underestimated the job! Any lawyers out there?
My contractor wrote a contract that called for a 500 sq ft patio. As it turns out, when he modified his original drawing (per my request), the patio is now 550 sq ft. Since he only bought 500 sq ft of materials, am I obligated to pay him for the extra 50 sq ft? I don't want to be obnoxious, but I don't want to be a doormat, either. Does anyone know where I stand legally in Illinois with this?
6 Answers
- I'm_BoredLv 41 decade agoFavorite Answer
I can't specifically comment on the laws in IL, but in general, the answer to this question is based on what documentation you approved prior to the job's start. If he provided you with a drawing of some sort, or a list of materials that didn't change when the s.f. changed, I would think you would be responsible. If his contract states something along the lines of "work includes all materials and labor to complete 550 s.f. patio" then he is liable.
I don't know what type of materials are involved, but if you're not talking about a lot of money, you should consider how good your contractor was on the whole, and how low his original price came in compared to other contractors. This cost may make the difference between making a profit or not. If he did a nice job and he seems like an honest guy, I'd let it go.
Another compromise would be to suggest splitting the difference with him, or ask him for his actual materials invoice (not marked up) and pay that cost.
Source(s): I work for a contractor. - 1 decade ago
I'm not a lawyer, but it seems that you broke the contract first by asking him to modify the original plan. A bigger plan calls for more material. More cost to him. Why should he eat the cost when it was your request?
As long as the extra cost is in proportion to the original plan, I don't think you have much to argue about.
- dtLv 51 decade ago
Are you kidding? You initiated a change order that caused the increaseso you need to pay the extra. I know you are concerned about being a doormat but this is obvious. Pay the bill.
- condonLv 44 years ago
It ability this restoration has been greater desirable than till now theory. those job losses happened in 08 commencing 10 months in the previous Obama took place of work, and in elementary terms 3 months into Obama's Presidency. this implies Obama inherited a worse financial mess than all of us theory.... As for it being suspicious, there is not any longer something to characterize Bush replaced into doing something to impression job comments on the time.... this could be a typical revision that occurs each and each 3 hundred and sixty 5 days.... the numbers are probable greater desirable than primary as a results of fact the recession replaced into huge. edit: to those BLAMING OBAMA, did it take place to you to examine the dates?... those job losses are being counted long in the previous Obama took place of work to in elementary terms 3 months into his presidency.
- How do you think about the answers? You can sign in to vote the answer.
- 1 decade ago
ok..i had no way of emailing you... about the question of mine you answered... she found out about the diamond ring because she came over when no one was home and started going through stuff... now she doesnt call me... just thought id answer your question... thanks for answering mine... have a good day...
Im not in Illinois... but id say the extra 50 sq ft. is not yours to pay... you shouldnt have to pay for something you dont want...
- Anonymous1 decade ago
If he has to buy extra materials and there's extra time to install then yes, and besides you gave your ok.