What is an average time for a bath remodel (add a sink, install a new shower, no tub)? Thank you in advance.?

2017-11-02T11:05:17Z

plus new tile in shower and on floor (total room is about 15x6)

B2017-11-02T15:15:47Z

it's been 8 weeks, because not every day is a work day. slow, long, painful. should have determined more 'end' dates. demolition was one day, then an electrician started and walked off the job, etc.

?2017-11-02T11:37:46Z

one day

Firestormer2017-11-02T11:37:25Z

3 or 4 days. The longest part is allowing for the waterproofing to set properly