Yahoo Answers is shutting down on May 4th, 2021 (Eastern Time) and beginning April 20th, 2021 (Eastern Time) the Yahoo Answers website will be in read-only mode. There will be no changes to other Yahoo properties or services, or your Yahoo account. You can find more information about the Yahoo Answers shutdown and how to download your data on this help page.
Trending News
In Microsoft Project, when I update the % complete, it changes my start/finish times. Why?
How do I stop that from happening?
2 Answers
- Project ManagerLv 51 decade agoFavorite Answer
There's a long answer, and a short answer.
The long answer involves discussing how you have set up your project tasks and how you are entering your progress information. This problem is probably symptomatic of other issues that may need to be addressed. It also depends on what Calculation options you have set Tools->Options->Calculation
The short answer is that % Complete in MS Project is Schedule Percent Complete. If you started two weeks ago and are supposed to be finished tomorrow, but your report only being 50% done, then Project assumes you need another 2 weeks to get the job done.
To avoid this, don't use the % Complete field but insert the Physical Percent Complete field/column into your view and use that instead.