Yahoo Answers is shutting down on May 4th, 2021 (Eastern Time) and beginning April 20th, 2021 (Eastern Time) the Yahoo Answers website will be in read-only mode. There will be no changes to other Yahoo properties or services, or your Yahoo account. You can find more information about the Yahoo Answers shutdown and how to download your data on this help page.
Trending News
Which regulatory bodies must be contacted before work can begin updating a 400ton boiler system in Wisconsin?
Which regulatory bodies must be contacted before work can begin updating a large boiler system in Wisconsin?
Which regulatory bodies must be contacted once work has finished updating a large boiler system?
The concept is that the boiler will simply be brought up to code in regards to its safety valving on the gas train and controlling mechanisms will be upgraded from mechanical linkages. There will be no increase in emissions and no increase in capacity.
1 Answer
- gatorbaitLv 71 decade agoFavorite Answer
Contact:
Wisconsin Department of Commerce
Division of Safety & Buildings Division
Contact the Boiler and Pressure Vessel Program
- Boiler and Pressure Vessel Inspector districts map
- You may email Boiler and Pressure Vessel technical questions to sbboilertech@commerce.state.wi.us
- You may fax Boiler and Pressure Vessel technical questions to 608-283-7420.
- The supervisor of boiler inspectors is Rick Merkle, rick.merkle@wisconsin.gov, 262-521-5065.
- Boiler and Pressure Vessel Code Advisory Council
- The S&B Credentialing Unit email is madisoncred@wisconsin.gov