Yahoo Answers is shutting down on May 4th, 2021 (Eastern Time) and beginning April 20th, 2021 (Eastern Time) the Yahoo Answers website will be in read-only mode. There will be no changes to other Yahoo properties or services, or your Yahoo account. You can find more information about the Yahoo Answers shutdown and how to download your data on this help page.

mkm
Lv 4

Basis of Key handing-over on completion of Building..?

Could anyone make me aware of the process and applicability in "Key handing over" after completion ready for occupancy by the construction contractor with respect to:

- Fixtures and fittings involved in the building.

- Interiors

- Landscaping including gate and boundary.

The agreed term being 'key handing over ready to occupy against square feet area basis, specific applicability may be made known.

1 Answer

Relevance
  • HMT
    Lv 7
    1 decade ago
    Favorite Answer

    If you are satisfied about the completion of Building and if the builder has received a Completion Certificate from the municipality then you may take possession.