Yahoo Answers is shutting down on May 4th, 2021 (Eastern Time) and beginning April 20th, 2021 (Eastern Time) the Yahoo Answers website will be in read-only mode. There will be no changes to other Yahoo properties or services, or your Yahoo account. You can find more information about the Yahoo Answers shutdown and how to download your data on this help page.

What is the formula used?

I used to know what formula to use for a problem like this, but cannot remember anymore.

If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how long would the job take if Sam, Lisa, and Tom worked together to complete it?

Any help would be appreciated.

3 Answers

Relevance
  • Anonymous
    9 years ago
    Favorite Answer

    first u need to find how much each person works in 1 day.

    here Sam does 1/4 th of the job in one day.

    lisa does 1/6 th of the job and tom does 1/2 of the job in one day.

    so in one day together they can do 1/4+1/6+1/2 = 11/12 of the job in one day.

    so they can do the whole job in 12/11 days = 1 1/11 days

  • Sam does the job in 4 days, which means he does 1/4 of the job in a day

    Lisa does the job in 6 days, which means she does 1/6 of the job in a day

    Tom does the job in 2 days, which means he does 1/2 of the job in a day

    1/4 + 1/6 + 1/2 =>

    3/12 + 2/12 + 6/12 =>

    11/12

    Working together, 11/12 of the job is completed in 1 day

    1 / (11/12) => 12/11

    It will take them 12/11 days to complete the job

  • I'm the best in my college so i can help you

    sam does 25% of the job in a day

    lisa does it 16.67%=100%/6

    tom does it 50%

    adding them= 1100%/12

    let x be the number of days

    we need 100% so

    1100%*x/12=100%

    the answer is 12/11 days

    1 day and 7854.5 seconds=1 day, 2 hours,10 minutes and 54 seconds